Actual Schedule for Team 28, Project 2
Oct 28- Team met to decide schedule and team duties
Oct 30- Initial Brainstorming session
Nov. 1- Brainstorming and Initial Construction of Wings
Nov. 3- Finish Wings and Attach wings and Tail to Mousetrap and fuselage
Nov. 6- Work on powering Airplane and initial launching device, Testing
of launch vehicle
Nov. 8- Worked for 8 hours with absolutely nothing to show, tested
launcher and it broke many times. Redesigned launcher.
Nov. 10- Tested new launcher design on the ramp. It was a total failure.
Launcher redesigned, tested and IT WORKED decently, also created budget
Nov. 11- Judgment day. We passed, sort of.
Nov. 11- Met to discuss results and work on web site.